From accepted quote to first purchase order

The builder has accepted Harlow Mechanical’s price for Bowen Hills Health Hub. Before Dan orders the controls package, he needs to know which option the builder bought and whether the supplier’s price still fits.

Ordin design preview · Fictional jobs and figures · Australian dollars, excluding GST

Estimate · Priya Nair

Start with the revision the builder signed

Priya attaches the acceptance letter to revision C. It includes the optional tenant metering points and leaves out the acoustic lagging. Dan can open the letter and see exactly what he has to deliver.

Q-1192 · Revision C
Accepted base quote
$1,268,028
Tenant metering · option O1
+$36,200
Accepted contract
$1,304,228

Handover · Dan Okafor

Give the project manager the buying allowance

Dan accepts the handover. The estimate carries line 4.01 and the accepted option into the controls budget. The builder pays $36,200 for tenant metering, but the estimate sets aside $29,500 to buy it.

P-2440 · Cost centre 40 · Controls
Controls subcontract · line 4.01
$148,500
Tenant metering · O1 cost
+$29,500
Available to order
$178,000

Purchasing · Dan Okafor

Catch the overrun before placing the order

Dan raises the first purchase order for this cost centre against line 4.01 and O1. Apex has increased its package price. Dan records the reason and sends it to Sam, the owner. Even an order within allowance needs a second approver.

PO-3052 · Apex Controls
Available allowance
$178,000
Supplier’s package price
$189,700
Amount over allowance
$11,700

Awaiting a second person’s approval

Approval and accounts · Sam Whitlock

See what the decision costs

Sam approves the extra $11,700 to keep the installation date. Dan issues the order, committing $189,700. When accounts approves the matching bill for the full delivery, that commitment becomes an actual cost. With the contract price and other costs fixed, forecast profit falls $11,700, about 0.9 percentage points of job margin.

P-2440 · Controls budget after bill approval
Original allowance
$178,000
Open commitment
$0
Actual supplier cost
$189,700
Remaining allowance
−$11,700