Construction job costing

Construction job costing: what will this job cost to finish?

A project manager has a ductwork cost centre that is half built, a fabrication order that is part billed and a crew that is running behind. Here is the cost-to-complete sum a job costing system should do for them, and the question to ask in a demo.

Join the early-access waitlist

Ordin design preview · Proposed workflow · Fictional job and figures · Australian dollars, excluding GST

The four numbers behind cost to complete

Job costing for a trade contractor is not the same as bookkeeping. Accounts records what has been billed. The project manager needs to know what the job will cost by the end, while orders are still open and the crew is still on site. That answer comes from four numbers kept apart on each cost centre.

Budget
The cost allowance carried from the accepted quote, plus approved variations (change orders).
Committed
Purchase orders and subcontracts placed but not yet billed. Only the unbilled part counts.
Incurred
Cost already in: approved supplier bills, approved timesheets and other recorded spend.

The fourth is the remaining forecast: the cost the project manager still expects but has not ordered, such as labour hours yet to be worked. Cost at completion is incurred + open commitments + remaining forecast. Forecast margin is the contract value for the cost centre less that cost.

P-2471 · Kemp Street Offices, Levels 4 to 6 · Cost centre 30 · Ductwork

Start with what the builder accepted

Harlow Mechanical won the Kemp Street fitout. The accepted quote prices ductwork at $262,000 and allows $205,000 to deliver it. That allowance becomes the cost centre budget at handover, so the project manager, Dan, isn’t retyping the estimate into another system.

Cost centre 30 at handover
Contract value · ductwork$262,000
Cost budget from the accepted quote$205,000
Margin at budget$57,000 · 21.8%

A variation the builder hasn’t approved yet stays out of both the contract value and the budget. It shows separately as pending, so it can’t prop up the forecast before anyone has agreed to pay for it.

Week 9 · Dan Okafor, project manager

Count the part-billed order once

Dan ordered the fabricated duct from Brightline Sheetmetal on one purchase order for $120,000. Brightline has delivered and billed $72,000 of it. Accounts has approved that bill, so $72,000 is incurred and only $48,000 is still committed. The crew has booked 440 hours at a $95 cost rate, and a site counter purchase of $1,800 has gone through without an order.

Cost at completion · week 9
LineAmount
Incurred · Brightline bill against PO-3108$72,000
Incurred · labour, 440 h × $95$41,800
Incurred · site counter purchase$1,800
Open commitment · PO-3108 not yet billed$120,000 order less $72,000 billed$48,000
Remaining forecast · labour, 520 h × $95$49,400
Remaining forecast · fixings and sealant$2,600
Cost at completion$215,600
Against the $205,000 budget$10,600 over
Forecast margin · $262,000 − $215,600$46,400 · 17.7%
The double count to look for
Full PO value + everything incurred + remaining forecast$120,000 + $115,600 + $52,000$287,600
Correct cost at completion$215,600
Overstated by the billed part of the order$72,000

When a bill is matched to its order, the committed figure should fall by exactly the amount the incurred figure rises. If the system counts the whole order as committed and also counts the bill, a healthy job looks like a disaster. If it drops the order when the first bill arrives, the remaining $48,000 vanishes and the job looks better than it is.

The decision · Dan and Sam Whitlock, owner

Buy the fittings, or keep fabricating on site?

Dan is $10,600 over on this cost centre. Brightline offers to shop-fabricate the remaining fittings for $9,000. Dan’s leading hand estimates that saves 140 of the 520 crew hours still to work. Dan puts the option into the forecast before he raises the order.

If Dan raises the $9,000 order
Incurred, unchanged$115,600
Open commitment · $48,000 + new $9,000 order$57,000
Remaining forecast · 380 h × $95 + $2,600$38,700
Cost at completion$211,300
Forecast margin$50,700 · 19.4%

The order saves $4,300 against the current forecast ($13,300 of labour less the $9,000 order). It doesn’t bring the cost centre back to budget, so Dan sends it to Sam with the reason and the new forecast. Sam approves it. The order then shows as committed and the 140 hours come out of the remaining forecast at the same moment, so the margin moves once.

The question to test in a demo

Ask the vendor to do this liveOpen a cost centre with a part-billed purchase order. Show committed, incurred and remaining forecast as separate figures. Now approve another bill against that order. Does committed fall by the same amount incurred rises, and does cost at completion stay the same?

Then ask:

  • Where does the budget come from: the accepted quote revision, or someone retyping it?
  • How does a pending variation (change order) show, and when does it move into the contract value?
  • Can a project manager change the remaining forecast hours, and who sees that change?
  • Which purchase orders need a second approver, and is the approval kept with the order?
  • Where does labour cost come from: approved timesheets at a cost rate, or the payroll file a fortnight later?
  • Which system holds the ledger, and which figures come back from it?

In Ordin, this cost-to-complete view is a proposed design. The planned Australian pilot hands sent invoices to Xero, which keeps the ledger and payments. Follow another Harlow job from accepted quote to its first order in the quote to purchase order walkthrough.